Sep 04

Vine Street Improvements - 32nd to Caballo Pl. (DPW 12-12J-1)

Posted on September 4, 2018 at 11:33 AM by Caryn Jackson

August 31, 2018 Update (PDF)
Waterlines, streetlight conduits, and the gas mains have been installed. Concrete curbs, gutters, and ramps are complete. Contractor is performing the grading of the road to create the sub-grade foundation (8-31-2018).