Following the closure of the bid submittal period, bids will be publicly opened and read for performing work as follows: Furnishing all labor, materials, equipment, and performing all work necessary and incidental to the construction of the project known as Creston Road Sewer Upgrades - Ferro to Tanner, DPW PROJECT NO. 18-28, according to drawings and specifications prepared by the City of El Paso de Robles and according to the Contract Documents. The work shall include but is not limited to, demolition and removal of existing sewer mains and appurtenant structures, installing new sewer mains and appurtenant structures, trench restoration and pavment resurfacing,restoring pavement markings and striping, as needed, and final testing of pipes and structures, including all incidentals for a complete and statisfactory completion, all as shown on the plans and/or as specified herein.
Project is to be completed within Twenty (20) WORKING days from the date specified in the Notice to Proceed. The Contractor shall pay to the City of El Paso de Robles the sum of Three Hundred Dollars ($300.00), for each and every calendar day’s delay in finishing the work in excess of the calendar day completion time.
|