Following the closure of the bid submittal period, bids will be publicly opened and read for performing work as follows: Furnishing all labor, materials, equipment, and performing all work necessary and incidental to the construction of the project known as Country Club Neighborhood Pavement Rehabilitation, DPW Project No. 21-13, according to drawings and specifications prepared by the City of El Paso de Robles and according to the Contract Documents. The work shall include but is not limited to, sewer manhole rings and covers, dig-out repairs, placement of HMA and leveling of course, construction of cross-gutter, curb and gutter and restoration of pavement markings and striping, all as shown on the plans and/or as specified herein.
Project is to be completed within Seventy (70) WORKING days from the date specified in the Notice to Proceed. The Contractor shall pay to the City of El Paso de Robles the sum of Five Hundred Dollars ($500.00), for each and every calendar day’s delay in finishing the work in excess of the calendar day completion time.